Project Spotlight
Project Scope
To replace an existing culvert on Chippewa Creek with a new 420 metric tonne concrete box culvert in North Bay, ON
Challenges
Diverting the high flow water of Chippewa creek with only 8 weeks allowed to complete the project.
Methodology to overcome challenges
- Installing erosion control measures such as silt fence, turbidity curtains and silt bags
- Divert the watercourse by installing a temporary dam to direct the flow into culverts capable of handling a 100 year storm for Chippewa Creek
- Dewatering the work area
- Removing all species from their habitat
- Installing a proven compacted granular base to a pre determined grade
- Sink the culvert into the creek bed to create a natural ecosystem
- Careful planning of culvert delivery, positioning and handling with crane assistance
- Complete vegetation, guard rail, concrete and asphalt restoration
Previous
Next